1. Prerequisite Regulatory Documents

Before submitting drawings on the Balady portal, project owners or developer representatives must ensure ownership and site geometry records carry no discrepancies:

  • Updated Electronic Deed: Digitized via Najiz with accurate boundary lengths matching current municipal street widths.
  • Cadastral Survey Decision (Qarar Masahi): Staked on site using RTK-GPS by an accredited office (GIS Land Surveying).
  • Geotechnical Report (SBC 303): Borehole testing confirming soil bearing capacity, excavation method, and concrete sulfate protection requirements.

2. Technical Package & SBC Review

All design sheets submitted through Balady must carry Saudi Council of Engineers (SCE) stamps from an accredited engineering firm across all required disciplines:

  • Architecture & Planning (SBC 1101): Respecting residential ground coverage limits (typically 70% ground floor + 10% detached annex), neighbor setbacks (minimum 2m except blind zero-lot sides), and street frontage setbacks (generally 1/5 of street width).
  • Energy Conservation (SBC 602): Wall/roof R-values, thermal bridge continuity, lighting power density schedules, and HVAC efficiency ratings.
  • Structural & MEP Safety (SBC 301/304/401/501/701): Seismic load resistance, electrical panel load balance, and plumbing drainage venting.

3. Common Rejection Causes in Riyadh

Rejection TriggerTechnical CauseCorrective Step
Envelope Energy FailureDiscontinuous wall/column insulation or high window-to-wall heat gainRecalculate glazing SHGC & specify insulated structural concrete/block details under SBC 602
Survey MismatchDeed dimensions diverge from municipal planning gridExecute parcel boundary update via Balady survey department prior to architectural submission
RCRC Urban Zone Non-ComplianceApplying generic finishes inside Wadi Hanifah or Sports Boulevard corridorsAlign elevations, matte earth tones, and local stone bases with RCRC design manual

4. Supervision, IDI & Final Completion

Once Balady approves the technical package, issuing the active Building Permit requires binding a licensed supervising engineering office (Site Supervision) and Inherent Defects Insurance (IDI) where applicable. Contractors may not commence pouring before stage inspection sign-offs are logged through construction to obtain the final Completion Certificate and Saudi Electricity Company meter hookup.